Capital Projects

  • The Enlarged City School District of Middletown is fortunate to have a supportive community that enables the district to improve its physical plant through Capital Projects, which are presented to voters as referendums separate from the annual budget. We will use this space to chronicle these projects from the developmental stage through completion.

    If you have any questions about the current or past voter-approved projects, please email construction@ecsdm.org.


  • Twin Towers Middle School Capital Improvement Project

    Twin Towers Middle School opened its doors more than 80 years ago, and is considered the historical icon of the district, as well as the City of Middletown. It opened as the Middletown City School District's new high school, and then, in 1975, was converted to a junior high school. Touting its Gothic architecture and impressive bell towers at each end of the front of the school, it is also one of Middletown's oldest jewels. For long-time community members, and those who return, the building brings back cherished memories. To provide a healthier, safer and engaging environment to meet the changing needs of the scholars, as well as a continued increase in enrollment, the school requires significant renovation, modernizing and repair. Thanks to a positive community vote for this project, the Middletown School District will embark on these improvements over the next five years at Twin Towers. See the project progress

Project Schedule

Phase 1: Spring and Summer 2023


  • Past Capital Projects

    December 10, 2019 Referendum Projects

    ➣Monhagen Middle School:  Sports courts & dehumidification-controls upgrade
    ➣Presidential Park Elementary School:  Grades 3-5 playground & Parking lot, drainage and current playground repair
    ➣Twin Towers Middle School:  Remove carpet in 16 rooms & asbestos removal involved with existing tiles
    ➣Maple Hill Annex at Truman Moon:  Sidewalks-parking lot-fencing-lighting
    ➣Maple Hill Elementary School:  Dehumidification - controls upgrade
    ➣Middletown High School:  Entrance flooring 

    December 4, 2018 Referendum Projects

    ➣Middletown High School:  New Library Media Center & cafeteria
    ➣Twin Towers Middle School:  Masonary Restoration & roofing and flashing repairs
    ➣Monhagen Middle School:  Roofing replacement & garage roofing replacement
    ➣Maple Hill Elementary School:  Roofing replacement

All 180 wells are drilled!!!

  • August 18, 2023: Well drilling is complete. To read more about the other projects, go to the  project progress page.

    Construction site drill rigs and heavy equipment and construction workers.

Geothermal wells 169 done and lighting is underway

  • August 4, 2023: As of today, 169 wells out of 180 has been drilled, plus much more site work is in progress. To read more, go to the  project progress page.

    Construction site drill rigs and heavy equipment and construction workers.

Bus Loop, Geothermal Wells and Other July Progress Updates

  • July 28, 2023: Buses test the newly contructed bus loops. One hundred and fifty-nine wells out of one hundred eighty are complete. Masonry work continues.  To read more, go to the  project progress page.   

    Two yellow school buses parked on newly constructed bus loop.


  • See the Twin Towers Capital project progress.  

    If you have any questions about the current or past voter-approved project, please email construction@ecsdm.org.