Twin Towers Middle School opened its doors more than 80 years ago, and is considered the historical icon of the district, as well as the City of Middletown. It opened as the Middletown City School District's new high school, and then, in 1975, was converted to a junior high school. Touting its Gothic architecture and impressive bell towers at each end of the front of the school, it is also one of Middletown's oldest jewels. For long-time community members, and those who return, the building brings back cherished memories. To provide a healthier, safer and engaging environment to meet the changing needs of the scholars, as well as a continued increase in enrollment, the school requires significant renovation, modernizing and repair. Thanks to a positive community vote for this project, the Middletown School District will embark on these improvements over the next five years at Twin Towers.
One of the most exciting parts of this project is the installation of geothermal heating and cooling, this introduces modern and clean energy into the district. To learn more about geothermal energy and the NYS initiative, go to the NYSERDA website.
Task |
Phase 1 Infrastructure |
Phase 2 Additions and Alterations |
SED Permitting |
Complete |
March 2024 (Est.) |
Engagement+Outreach |
March-August 2023 |
March-August 2023 |
Bidding |
March 2023 |
March 2024 |
Pre-Construction |
April-May 2023 |
Fall 2023-Spring 2024 |
Construction |
June 2023-August 2024 |
Spring 2024 Start |
Project |
Timeframe ( Approximates) |
Geothermal Well Drilling |
September 2023 |
Asbestos Abatement Crawl Spaces |
August 2023 |
Drop off/Pick up Loop |
August 2023 |
Masonry |
September 2023 |
Window Replacement |
April 2024-September 2024 |